Stucco, bathroom, and (slow) roof progress

Today, the color coat for the stucco went on. It hasn’t dried yet, and my understanding is that it will darken by a couple of shades as it does.

Continue reading “Stucco, bathroom, and (slow) roof progress”

Lots of progress to report!

There has been so much activity in the last week that it has been hard to keep up with everything!

The cabinets have arrived in boxes and are packed floor to ceiling in the addition. Installation of the cabinets will begin this week.

We have purchased all of the appliances. We were able to get several as “open box” and “floor model” specials to save a little money. The appliance installer will measure for the appliances next Friday, with installation of them scheduled for Friday, November 2. Hopefully everything goes smoothly with the cabinet installation.

Continue reading “Lots of progress to report!”

Progress

There has been some progress to report. I’ve finally come to accept the cost increases I reported in my last post.

We have hired a plumber to upgrade the water service to the 1 1/2″ required. Our contractor has worked through the final details of the permit, and we finally have the official permit. The police department will allow us to park our car on the street during construction. The contractor has finally given us a rough start date for the foundation work for the addition (in the next week or two). The project timeframe has been extended from 38 weeks to 1 full year.

Continue reading “Progress”