The wood floors have been installed, and the bathrooms are ready to tile.
With all of the floor leveling that was done, the front door would not swing open without cutting it down.
Continue reading “Hardwood flooring / bathrooms ready for tile”
Orth House II Renovation blog
The wood floors have been installed, and the bathrooms are ready to tile.
With all of the floor leveling that was done, the front door would not swing open without cutting it down.
Continue reading “Hardwood flooring / bathrooms ready for tile”
Our new oak floor has been installed on the main floor of the addition, stairs, and landing. It looks terrific! It’s unfinished and dirty right now. They will be sanding it down and finishing it next week.
Some progress on the renovation continues, albeit slowly.
The roofing delay we experienced was mostly due to them running out of shingles. The shingle was a special order, and only part of the shipment arrived. So they stopped for a month or so while they waited for the rest to arrive.
Fortunately, it arrived last week, and they returned to finish the addition’s roof and proceed in the main house.
Continue reading “Other progress – roofing, stairs, and pump”
Work had been progressing at a good pace.
The street, driveway, and yard were patched and repaired after the water service was upgraded.