There has been some progress to report. I’ve finally come to accept the cost increases I reported in my last post.

We have hired a plumber to upgrade the water service to the 1 1/2″ required. Our contractor has worked through the final details of the permit, and we finally have the official permit. The police department will allow us to park our car on the street during construction. The contractor has finally given us a rough start date for the foundation work for the addition (in the next week or two). The project timeframe has been extended from 38 weeks to 1 full year.